Wexmoor Row, Bristol

← All projects / Residential / Bristol

Wexmoor Row

Client
Wexmoor Housing
Size
2,800 m²
On site
March 2024 to June 2025
Status
Handed over
Wexmoor Row, finished

The job

Twelve family houses in two mirrored terraces, timber frame on a concrete raft.

Here Sitework built

Wexmoor Row

Client
Wexmoor Housing
Architect
Hollin Lowe Architects
Structural engineer
Pentre Structures
Main contractor
Sitework
Site manager
Rohan Varghese
Start
March 2024
Completion
June 2025
Scope
12 houses, 3 floors
Contract value
£6.4 M

+44 20 7946 0412Handed over

How we built it

The plot was an old bus depot with a slab we could not see under. We broke it out in week two, found two fuel tanks nobody had drawn and still kept the programme, because the tanks went out on the same lorries as the rubble.

Each terrace stands on one concrete raft. The timber frames arrived from the factory numbered by house, went up in nine working days per terrace and were watertight before the first winter storm.

Site diary

  1. Mar 2024Site cleared, old depot slab broken out
  2. Jun 2024Both rafts poured, drainage connected
  3. Oct 2024Timber frames up, roofs on
  4. Feb 2025Brick slips and windows complete
  5. Jun 2025Twelve sets of keys handed over