← All projects / Industrial / Daventry
Northgate Hall
- Client
- Northgate Logistics
- Size
- 18,500 m²
- On site
- May 2023 to February 2024
- Status
- Handed over

The job
A logistics hall with 24 loading docks, built in 41 weeks on a working estate.
How we built it
Our client had a contract that started on a fixed Monday, with or without a building. We split the hall into three zones, so steel went up in one while the floor was poured in the next and the cladding closed the third.
The floor is one of the flattest we have laid: 18,500 square metres of fibre reinforced slab, laser screeded in eleven pours, ready for racking eleven metres high.
Here Sitework built
Northgate Hall
- Client
- Northgate Logistics
- Architect
- Calder Ridge Partnership
- Structural engineer
- Pentre Structures
- Main contractor
- Sitework
- Site manager
- Halvard Teague
- Start
- May 2023
- Completion
- February 2024
- Scope
- 1 hall, 24 docks
- Contract value
- £21 M
+44 20 7946 0412Handed over
41
weeks from dig to keys
24
loading docks
11
slab pours, laser screeded
0
lost-time injuries