Fenwright Offices, Leeds

← All projects / Commercial / Leeds

Fenwright Offices

Client
Fenwright Rail
Size
6,100 m²
On site
April 2021 to August 2022
Status
Handed over
Fenwright Offices, finished

The job

Brick and glass headquarters for a rail operator, next to a live track.

Here Sitework built

Fenwright Offices

Client
Fenwright Rail
Architect
Calder Ridge Partnership
Structural engineer
Marsh Quay Consulting
Main contractor
Sitework
Site manager
Halvard Teague
Start
April 2021
Completion
August 2022
Scope
6 floors
Contract value
£17 M

+44 20 7946 0412Handed over

How we built it

The site runs along a live railway, so the line could never see our crane swing over it. We fitted the crane with a zoning system and planned every heavy lift around the timetable.

Inside, the offices are column free from facade to core. That meant long post-tensioned slabs, poured at night when the trains were quiet.

Site diary

  1. Apr 2021Rail safety plan approved
  2. Sep 2021Piles and basement complete
  3. Feb 2022Post-tensioned slabs poured at night
  4. May 2022Brick and glass facade closed
  5. Aug 2022Staff move in